ESTIMATED FINANCIAL REQUIREMENTS
FOR
SECOND PHASE
BUILDINGS
1 Vocational Trade and Skills building ......................................................................
1 Laboratory, Library building ..................................................................................
EQUIPMENT - For Trade and Skills building
For Men - Auto Mechanics, Carpentry- Welding- Farming, Plumbing, Computers and
Typewriters ..............................................................................................................
For Girls - Sewing machines, Knitting, Home Economics, Farming, Computers and
Typewriters ..............................................................................................................
EQUIPMENT - Computers
Musical instruments, Sound Systems, Generators ......................................................
TOTAL ESTIMATED BUDGET FOR SECOND PHASE .....................................
COST
$50,000
$70,000
$50,000
$30,000
$25,000
$225,000